Monday, September 17, 2012


Q.no 1-
What the function are typically performed by a production control department ?

Ans –
Production control department responsibilities consist of
1. Loading—checking the availability of material, machines, and labour. The MRP system
plans for material availability. CRP converts the material plan into machine and
labour requirements, and projects resource overloads and under loads. Production
control assigns work to individual workers or machines, and then attempts to
smooth out the load to make the MRP schedule "doable." Smoothing the load is
called load levelling.
2. Sequencing—releasing work orders to the shop and issuing dispatch lists for individual
machines. MRP recommends when orders should be released (hence the name,
planned order releases). After verifying their feasibility, production control actually
Releases the orders. When several orders are released to one machine center, they must
be prioritized so that the worker will know which ones to do first. The dispatch list
contains the sequence in which jobs should be processed. This sequence is often based
on certain sequencing rules.
3. Monitoring—maintaining progress reports on each job until it is completed. This is
important because items may need to be rescheduled as changes occur in the system.
In addition to timely data collection, it involves the use of Gantt charts and input/output
control charts.
Q.no 2 –
Explain Johnsons rule and its Procedure .
Ans-Since few factories consist of just one process, we might wonder if techniques exist that will
produce an optimal sequence for any number of jobs processed through more than one
machine or process. Johnson's rule finds the fastest way to process a series of jobs through a
two-step system in which every job follows the same sequence through two processes. Based
on a variation of the SPT rule, it requires that the sequence be "mapped out" to determine
the final completion time, or makespan, for the set of jobs. The procedure is as follows:
1. List the time required to complete each job at each process. Set up a one-dimensional
matrix to represent the desired sequence with the number of slots equal to the number
of jobs.
2. Select the smallest processing time at either process. If that time occurs at process 1,
put the associated job as near to the beginning of the sequence as possible.
3. If the smallest time occurs at process 2, put the associated job as near to the end of the
sequence as possible.
4. Remove the job from the list.
5. Repeat steps 2-4 until all slots in the matrix have been filled or all jobs have been
sequenced.
Q.no 3-
Ans -
Item
1
2
3
4
5
Chocolate Mint
30
18
26
17
15
Peanut Butter
23
22
32
25
30
Short Bread
17
31
24
22
29
Fudge Delight
28
19
13
18
23
Macarooons
23
14
16
20
27




Matrix :
30
18
26
17
15
23
22
32
25
30
17
31
24
22
29
28
19
12
18
23
23
14
16
20
27

15
3
11
2
0
1
0
10
3
8
0
14
7
5
12
15
6
0
5
10
9
0
2
6
13

Crosses line not equal to order of matrix so,
15
3
11
0
0
1
0
10
1
8
0
14
7
3
12
15
6
0
3
10
9
0
2
4
13

                                                
15
3
11
0
0
0
0
10
0
7
0
15
7
3
12
15
7
0
3
10
9
0
2
4
13


Item

Chocolate Mint
5
Peanut Butter
4
Short Bread
1
Fudge Delight
3
Macarooons
2


Q. no -4
Answer –
Product
A
B
C
D
E
1
17
10
15
16
20
2
12
9
16
9
14
3
11
16
14
15
12
4
14
10
10
18
17
5
13
12
9
15
11

Matrix :
3
10
5
4
0
8
11
4
11
6
9
4
6
5
8
6
10
10
2
3
7
8
11
5
9

3
10
5
4
0
4
7
0
7
2
5
0
2
1
4
4
8
8
0
1
2
3
6
0
4

A
B
C
D
E
1
10
5
4
0
2
7
0
7
2
3
0
2
1
4
2
8
8
0
1
0
3
6
0
4

E
1
C
2
B
3
D
4
A
5

No comments:

Post a Comment